RIDOT reopens Stillwater Viaduct ahead of schedule 


SMITHFIELD, R.I. — During a tour of the Stillwater Viaduct in Smithfield, the Rhode Island Department of Transportation (RIDOT) announced that it will be reopening the bridge to traffic on Oct. 24, 2012. This new opening date is approximately five weeks ahead of schedule. The 80-year-old bridge — at 450 feet long with 11 spans including huge concrete arches over the water — has been closed to all traffic since March while RIDOT completely replaced the superstructure, made substructure repairs and performed minor concrete repairs to the bridge's arches. The replacement structure is the same width as the existing bridge, with sidewalks on both sides.

Through a $9.4 million contract with Northern Construction Services, RIDOT made use of precast components wherever possible and placed a $10,000-per-day incentive clause in the contract for every day ahead of schedule the bridge was open to traffic (maximum of 30 days). Additionally, the department coordinated closely with the community on the decision to close the bridge so the work could be accelerated. Originally the department considered phased construction that would have kept the bridge partially open to traffic, but would have taken three to four years to complete.

"This is the kind of transportation project we like to see: planned with community input, utilizing effective accelerated construction techniques, and, as a result, completed significantly ahead of schedule," Governor Lincoln D. Chafee said. "Going forward, when significant improvements or replacements are necessary, we will continue to explore innovative ways to execute them efficiently and come in ahead of schedule with minimum interruption of service."

RIDOT has witnessed success with other bridge projects using accelerated construction methods. In late 2010, RIDOT replaced the Round Top Bridge in Burrillville in just 41 days. More recently, this August the Department reopened the Frenchtown Brook Bridge in East Greenwich in only 33 days.

All future bridge projects will be evaluated to determine the feasibility of using accelerated construction methods. Not all bridges can be rehabilitated in this way. The impact to traffic (the use of these techniques often call for a total road closure), the complexity of utility relocations and the amount of work needed to be accomplished in the project must be taken into consideration.

Similar approaches are planned for the replacement of larger bridge structures in the next two years including the East Shore Expressway Bridge in East Providence, which carries traffic from I-195 East onto Exit 7 (Route 114) and over Warren Avenue, and the Barton Corner Bridge, which carries I-95 over Route 2 (Quaker Lane) on the Warwick/West Warwick line.

While RIDOT is opening the Stillwater Viaduct to traffic next week, minor construction activities will continue until late Spring 2013.
 


Links


Headlines From Around The Web

N.C. DOT to cut 400 positions (Winston-Salem Journal)
Georgia DOT commissioner resigns (Atlanta Journal-Constitution)
Georgia DOT loses another top manager (Atlanta Journal-Constitution)
New Road Signs Will Now Wait (The New York Times)
WYDOT staffer wins national post (Billings Gazette)
Schneider named acting IDOT director (The State Journal-Register)
Selection of MDOT director delayed (Hattiesburg American)




HubDOT Exclusive

In replacing the Willamette River Bridge, the Oregon Department of Transportation makes steps to ensure the structure's ecological footprint is as small as possible, leaving room for natural habitats to flourish.

  Bringing new life to the I-5 Willamette River Bridge

Webcasts


Related Engineering Channels